How to Calculate Schedule Variance
In the world of project management, staying on schedule is crucial to ensure successful project completion. One key concept you may have come across is schedule variance (SV). This metric helps project managers analyze and measure the progress of a project against its planned completion date. Here, we will provide you with an in-depth understanding of schedule variance and guide you through the process of calculating it.
What is Schedule Variance?
Schedule Variance (SV) is a metric used to measure the difference between the planned value (PV) and the earned value (EV) on a specific date during a project’s life cycle. The result indicates whether a project is progressing ahead or behind its original schedule.
A positive SV suggests that the project is running ahead of schedule, while a negative SV indicates that the project is lagging behind. Knowing your SV plays an essential role in understanding and addressing potential delays or inefficiencies in your project management processes.
Calculating Schedule Variance
There are two essential components required for calculating schedule variance: earned value (EV) and planned value (PV).
1. Earned Value (EV): Earned Value represents the completed work’s monetary value at a specific time during the project’s life cycle.
To calculate EV:
EV = % completion of work up to date x total budget at completion (BAC)
2. Planned Value (PV): Planned Value refers to the monetary value assigned to scheduled work to be completed on a specific date during a project’s life cycle.
To calculate PV:
PV = % planned work up to date x total budget at completion (BAC)
Now that we’ve obtained both EV and PV, we can calculate the schedule variance:
Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV)
Examples of Schedule Variance Calculation
Let’s look at an example to better understand the concept:
Assume you have a project with a total budget at completion (BAC) of $10,000. By the end of the first month, your project was supposed to have completed 30% of the overall work. However, your project team has only finished 25% of the work by that time.
1. Calculate EV:
EV = % completion of work up to date x BAC
EV = 25% x $10,000
EV = $2,500
2. Calculate PV:
PV = % planned work up to date x BAC
PV = 30% x $10,000
PV = $3,000
3. Calculate SV:
SV = EV – PV
SV = $2,500 – $3,000
SV = -$500
The negative SV value (-$500) indicates that the project is behind schedule.
Conclusion
Project management entails rigorous planning and constant monitoring to ensure success. Schedule variance is a valuable metric in helping project managers measure their project’s progress against its initial plan. Being able to calculate SV accurately allows for better decision-making during the course of a project and helps keep teams accountable and on track to deliver successful outcomes.